North Springs Improvement District
Booster Pump Station Chemical Feed System Improvements
ADS Engineering provided electrical and instrumentation design, programming and construction services for the Booster Pump Station chemical upgrade.


Project Highlights:
  • Design plant low voltage distribution system for the chemical building.
  • Chemical building lighting and grounding.
  • Chemical building fire alarm system.
Owner/Client:

Hillers Electrical Engineering, Inc.

CH2MHILL


Schedule:

Project design completed in 11, 2009

Project construction completed in 2010


Total Project Cost: $260,000.00