Project Highlights:
Schedule:
Total Project Cost: $65,000.00
Project Highlights:
- Design of the RTU for pump station upstream and downstream level measurement.
- Installation of the RTU.
- PLC Program creation.
- Interfacing through the communication with the plant SCADA
North Springs Improvement District
Schedule:
Project completed:
Pump station No.1 03, 2009
Pump station No.2 08, 2011